THE APPLICABILITY TECHNIQUE FOR MAKING TIME PLANS FOR MAINTENANCE OF TEHNICAL SYSTEMS

By
Držislav Vidaković ,
Držislav Vidaković
Contact Držislav Vidaković

University of Osijek, Osijek, Croatia

Zorislav Kraus ,
Zorislav Kraus

University of Osijek, Osijek, Croatia

Hrvoje Glavaš
Hrvoje Glavaš

University of Osijek, Osijek, Croatia

Abstract

The article gives an overview of techniques for making different types of time plans. Their advantages and disadvantages due to the requirements for maintenance planning of technical systems were analyzed. Reference is made to the possibility of increasing the efficiency of maintenance by applying suitable planning techniques and optimization solutions (that results with a better utilization of resources). Scheduling is the process and the necessity of monitoring the implementation of plans is stressed as well as necessity to update and create a database for future plans.

References

1.
Vidaković D, Lacković Z, Bubalo. T.: Utjecaj tehničke dijagnostike i održavanja na troškove građevinske mehanizacije. In: 12th International Conference on Organization, Technology and Management in Construction (SENET), Primošten, Zbornik radova na CD-u.
2.
Whiting A. Structural Integrity Inspection with Unmanned Aerial Vehicles, Aerecon. Vol. 10, Pristup. p. 02.
3.
Vidaković D, Bubalo. T.: Metode pogodne za vremensko planiranje aktivdnosti održavanja, 21.
4.
In: Conference Maintenance 2015, Šibenik, Zbornik radova. p. 20–30.
5.
Todosijević M, Marić A, Đorđević L, Gligorijević S. Radna sposobnost mašina i njihovo održavanje. Vol. 9, Journal of applied engineering science, br. p. 43-47,.
6.
p. 10 02.
7.
T.I.L.O.S. Tome-location planning softwarefor managing linear construction projects.
8.
Matejević B. Istorijski razvoj dinamičkog planiranja u građevinarstvu, Zbornik radova Građevinsko-arhitektonskog fakulteta u Nišu br. Vol. 27. p. 13-27,.
9.
Francis SP. Critical Chain Scheduling and Risk Management – Projecting Project Value from Uncertainty, Svjetski tjedan za upravljanje projektima. Hong Kong.
10.
Zlatanović M, Matejević B. Kriterijumi kvaliteta dinamičkih planova, Zbornik radova Građevinsko-arhitektonskog fakulteta u Nišu br. Vol. 25. p. 255-263,.
11.
Radujović M. i suradnici: Planiranje i kontrola projekata, Građevinski fakultet Sveučilišta u Zagrebu.
12.
Vidaković D. Karakteristike i problemi mrežnog planiranja u građevinarstvu. Vol. 78, M – Kvadrat br. p. 48-56,.
13.
Vidaković D. Optimalizacija vremenskih planova za građevinske projekte, 10. In: Internacionalni simpozijum iz project managementa – YUPMA, Zlatibor, Zbornik radova. p. 333-337,.
14.
Hegazy T, Shabeeb KA, elbeltagi E. Cheema T.: Algotithm for Scheduling with Multiskilled Constrained Resources. Vol. 126, Journal of CE and Management. p. 414-421,.

Citation

This is an open access article distributed under the Creative Commons Attribution License which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited. 

Article metrics

Google scholar: See link

The statements, opinions and data contained in the journal are solely those of the individual authors and contributors and not of the publisher and the editor(s). We stay neutral with regard to jurisdictional claims in published maps and institutional affiliations.